Thursday, December 12, 2019

it 191211 Floors

Fetch station inner floors complete ...

it 191210 plastering

Fetch station plumbing works ....of the inner parts only for plumbing pipe passage...
As well the wood work for slab removed..

it 191209 Plastering

Fetch station iron gate fixing....there is a challenge with land form...and some modifications needed to be done with gates....

it 191127 Concrete

Concrete works for polytank stand (slab) started and completed on same day....and allowed drying for 2 weeks....

it-gh 191126 steel bend

Steel bending works continue after wood work on pillars ....

it-gh 191122 Pillar Woodwork

Wood work continued and black poly was mat on the wood before iron rods to add finish touch without plastering... ....


Friday, November 22, 2019

it-gh 191121-23 Slab work and gate

I mobilized for wood and Work started with slab and lintel for polytank .....
2 days finished with lintel and slab...
As well the iron gate for the fetching station is getting progress... 

Saturday, November 9, 2019

191108 Block laying

The block laying for the fetching station began after the pillars were complete....at 7:30am...to 4:00pm.

191105 Pillar works

This day after several weeks with health issues.... I was relieved....and started with pillar works for the polytank stand....
The pillars reach a stage when started at 1:00pm GMT ...
The pillar works took 3 days to complete all four pillars......

Wednesday, October 30, 2019

it-gh 191018

The concrete works for the pillars and floors begun, works could not be completed
because rainfall set-in.........


Continued and finished fetching station concrete casting shown below in other to begin with pillar works...


it-gh 191016

I made order for sand and chippings for concrete to be prepared for the
fetching station concrete works.

it-gh 191014/15

Corrections for pillar irons were made to suit size for total concrete.

it-gh 191012

The iron pillars was set and boards taken to measurement for concrete.