190916 it-gh Mpasaso Waterstation
Thursday, December 12, 2019
it 191210 plastering
Fetch station plumbing works ....of the inner parts only for plumbing pipe passage...
As well the wood work for slab removed..
it 191209 Plastering
Fetch station iron gate fixing....there is a challenge with land form...and some modifications needed to be done with gates....
it 191127 Concrete
Concrete works for polytank stand (slab) started and completed on same day....and allowed drying for 2 weeks....
it-gh 191122 Pillar Woodwork
Wood work continued and black poly was mat on the wood before iron rods to add finish touch without plastering... ....
Friday, November 22, 2019
it-gh 191121-23 Slab work and gate
I mobilized for wood and Work started with slab and lintel for polytank .....
2 days finished with lintel and slab...
As well the iron gate for the fetching station is getting progress...
Saturday, November 9, 2019
191108 Block laying
The block laying for the fetching station began after the pillars were complete....at 7:30am...to 4:00pm.
191105 Pillar works
This day after several weeks with health issues.... I was relieved....and started with pillar works for the polytank stand....
The pillars reach a stage when started at 1:00pm GMT ...
The pillar works took 3 days to complete all four pillars......
Wednesday, October 30, 2019
it-gh 191018
The concrete works for the pillars and floors begun, works could not be completed
because rainfall set-in.........
because rainfall set-in.........
it-gh 191016
I made order for sand and chippings for concrete to be prepared for the
fetching station concrete works.
fetching station concrete works.