Friday, November 22, 2019

it-gh 191121-23 Slab work and gate

I mobilized for wood and Work started with slab and lintel for polytank .....
2 days finished with lintel and slab...
As well the iron gate for the fetching station is getting progress... 

Saturday, November 9, 2019

191108 Block laying

The block laying for the fetching station began after the pillars were complete....at 7:30am...to 4:00pm.

191105 Pillar works

This day after several weeks with health issues.... I was relieved....and started with pillar works for the polytank stand....
The pillars reach a stage when started at 1:00pm GMT ...
The pillar works took 3 days to complete all four pillars......