Wednesday, October 30, 2019

it-gh 191018

The concrete works for the pillars and floors begun, works could not be completed
because rainfall set-in.........


Continued and finished fetching station concrete casting shown below in other to begin with pillar works...


it-gh 191016

I made order for sand and chippings for concrete to be prepared for the
fetching station concrete works.

it-gh 191014/15

Corrections for pillar irons were made to suit size for total concrete.

it-gh 191012

The iron pillars was set and boards taken to measurement for concrete.



it-gh 191010

the steel bender started the bending works for the pillars



it-gh 191009

I made order for the iron rods for the pillar works and floor concrete works.




Tuesday, October 8, 2019

Monday, October 7, 2019

it-gh 191007

Profile setting
The land was set for profiling. the profile for the fetching station begun.