Wednesday, September 25, 2019

it-190925 mpasaso

# Borehole block covering started today, September 25, 2019...Mpasaso no.2 Started at 9am for profiling, 3pm for block laying due to some circumstances ....... Plastering and metal cover to be done the next day. # Pump is also fixed and tested ....water flowed fast immediately when pump is  switched on...

it-gh 190925

 Pump fixing by crystal drilling company ltd
 the pump was installed and tested successfully.





Tuesday, September 24, 2019

it-gh 190924 drilling

Drill done successfully with SMRS drill company.... The distance reached is 60m deep... Drill start about 1pm GMT and finished around 3:00pm...
 

Saturday, September 21, 2019

it-gh 190921

blog creation
estimate in processsion
drawing and work all in processionit-