Thursday, December 12, 2019

it 191211 Floors

Fetch station inner floors complete ...

it 191210 plastering

Fetch station plumbing works ....of the inner parts only for plumbing pipe passage...
As well the wood work for slab removed..

it 191209 Plastering

Fetch station iron gate fixing....there is a challenge with land form...and some modifications needed to be done with gates....

it 191127 Concrete

Concrete works for polytank stand (slab) started and completed on same day....and allowed drying for 2 weeks....

it-gh 191126 steel bend

Steel bending works continue after wood work on pillars ....

it-gh 191122 Pillar Woodwork

Wood work continued and black poly was mat on the wood before iron rods to add finish touch without plastering... ....