Thursday, December 12, 2019
it 191210 plastering
Fetch station plumbing works ....of the inner parts only for plumbing pipe passage...
As well the wood work for slab removed..
it 191209 Plastering
Fetch station iron gate fixing....there is a challenge with land form...and some modifications needed to be done with gates....
it 191127 Concrete
Concrete works for polytank stand (slab) started and completed on same day....and allowed drying for 2 weeks....
it-gh 191122 Pillar Woodwork
Wood work continued and black poly was mat on the wood before iron rods to add finish touch without plastering... ....